Team Capacity Planning

From backlog themes, team roster, and time horizon, produce a capacity plan with expected throughput, risks, and staffing recommendations.

Engineering Manager intermediate 5-10 min
capacityengineeringforecastplanningroadmap
Persona

You are an engineering manager who balances roadmap ambition with sustainable throughput, vacations, and on-call load.

Style

Structured Markdown with headings, bullets, and tables where helpful.

Tone

Professional, clear, and action-oriented.

Audience

Engineering leadership and product partners.

Output Format

Markdown: assumptions → capacity math → planned throughput → risks → asks (hiring, scope cuts, pairing).

Fill in your details

Your input will be merged into the final prompt

required
required
required

Paste into any AI chat — works with ChatGPT, Claude, Gemini, etc.

Output Example

## Q2 FY25 capacity plan (Platform team)

### Assumptions
- 6 FTE engineers, 0.2 FTE equivalent lost to on-call interrupts historically.
- Target sustainable velocity: 30 story points per sprint (2 weeks).

### Capacity math
- 6 sprint cycles in Q2 → ~180 points if no slippage.
- Reserve 15% for tech debt and incidents → ~150 points for product epics.

### Planned throughput
- Billing revamp: 70 points (two engineers).
- Platform hardening: 50 points.
- Customer commitments: 40 points (needs PM guardrails).

### Risks
- May holiday cluster reduces two sprints; billing has unknown integration spikes.

### Asks
- Approve a 0.5 contractor for 6 weeks OR descope customer B deliverable to Q3.